PRELIMINARY FOURTH QUARTER AND FINANCIAL YEAR 2008 RESULTS
February 26, 2008
Highlights
• Golar reports operating income of $13.9 million and a net loss of $57.7 million, which includes
Other Financial Items loss of $57 million largely relating to non cash interest rate swap valuation
losses and foreign currency exchange retranslation losses
• Spot traded vessel earnings performance improved over the quarter although spot market
softening moving into the first quarter 2009
• The FSRU Golar Spirit entered regasification service after smooth commissioning period
• Floating LNG cooperation with PTTEP now focusing on identified opportunities
• Golar signs Heads of Agreement with LNG Limited covering project participation in (40%) and
sole LNG –off-take from the Gladstone LNG project
• Continued strong market inquiry for FSRUs
• Golar suspends dividend payment to strengthen balance sheet in advance of near term project
opportunities
Financial Review
Results
Golar LNG Limited (“Golar” or the “Company”) reports a net loss of $57.7 million and operating
income of $13.9 million for the three months ended December 31, 2008 (the “fourth quarter”). Net
income has been negatively impacted by other financial items loss of $57 million largely relating to
non-cash interest rate swap valuation losses and foreign currency exchange retranslation losses.
Revenues in the fourth quarter were $59.5 million increased from $58.1 million for the third quarter
of 2008 (the “third quarter”). Headline spot charter rates retained the improvement from the third
quarter for the early part of the fourth quarter but began to fall toward the end of the fourth quarter.
Average utilisation increased from 83% in the third quarter to 84% in the fourth quarter. Fourth
quarter average daily time charter equivalent rates (“TCEs”) improved to $46,407 per day compared
to $43,443 per day during the third quarter.
The Golar Spirit was employed throughout the fourth quarter on charter to Petrobras, whilst the
Golar Winter entered the shipyard for FSRU conversion at the end of the third quarter and will
remain in the yard until the second quarter of 2009. The newly chartered in vessel Ebisu went on
hire soon after delivery at the end of the third quarter and will remain on hire through the first
quarter of 2009.
There were no dry dockings performed during the fourth quarter. The Hilli and the Gandria have not
been employed throughout the fourth quarter and are not expected to have earnings throughout 2009.
Measures remain in place to minimise operating costs on these vessels until chartering or project
opportunities arise.
Voyage expenses, which largely relate to fuel costs associated with commercial waiting time and
vessel positioning, decreased marginally from $11.0 million in the third quarter to $10.2 million for
the fourth quarter, aided by the decline in fuel costs and slightly improved utilisation. Vessel
operating expenses were higher at $16.0 million for the fourth quarter as compared to $14.6 million
for the third quarter whilst administrative expenses were lower at $4.1 million as compared to $4.7
million last quarter.
Net interest expense for the fourth quarter was $11.9 million, up slightly from $11.4 million for the
third quarter.
Other financial items were a loss of $57.0 million in the fourth quarter compared to a loss of $23.1
million for the third quarter. Long-term interest rates fell dramatically during the fourth quarter,
although have recovered to some extent since December 31, 2008, and the US dollar has also
strengthened significantly during the fourth quarter. Both these events, if sustained, are beneficial to
the Company in the long-term but create non-cash accounting losses in the short-term.
The largest contribution to this loss relates to non-cash interest rate swap valuation losses which
gave rise to a loss to the income statement of $23.4 million during the fourth quarter. In addition to
the $23.4 million charge a realised loss of $9.0 million has been incurred as a result of refinancing a
loan during the quarter that had a fixed rate of interest. However, the Company immediately entered
into an interest rate swap for a similar amount of the new debt at an interest rate approximately 1.1%
lower than the rate on the fixed rate debt. As of October 1, 2008 the Company commenced hedge
accounting for some of its interest rate swaps and as a result a further $26.0 million loss, which
would have been taken to the income statement, has been accounted for through other
comprehensive income (reserves).
Foreign currency exchange losses, amounting to $12.8 million, relate to the retranslation of net lease
obligations denominated in British Pounds, valuation losses in respect of foreign currency forward
contracts associated with FSRU capital commitments and other foreign currency retranslation losses
primarily relating to foreign currency deposits acquired under forward contracts to settle foreign
currency capital commitments.
The balance of other financial items charge relates to equity swap valuation losses, investment
impairment and the write off of various financing related expenses.
For the twelve months ended December 31, 2008 Golar reports a net loss of $10 million, operating
income of $132 million and operating revenues of $229 million as compared to, net income of $136
million, operating income of $121 million and operating revenues of $225 million for the year ended
December 31, 2007. The decrease in net income is largely accounted for by a $36 million decrease
in the level of gains on sale of assets and investments in 2008 and an increase in other financial
items loss in 2008 of $74 million.
Financing, corporate and other matters
The value of cash has significantly increased over recent months and the Board believes that market
sentiment has shifted somewhat from giving full appreciation to dividend flow to focus on the
strength of Company balance sheets. The Board also believes that the development of FSRU and
FLNG project opportunities will lead to attractive near term investment opportunities for the
Company. Taking this into account and the current squeeze in credit markets the Board has decided
to suspend the dividend payment for at least the next 2 quarters or until financial market conditions
normalise.
As previously reported the Company drew-down on a new $285 million revolving credit facility
during the fourth quarter. The facility refinanced the existing debt in respect of the Methane Princess
and the Golar Spirit and provided additional financing of approximately $80 million. Golar’s ability
to complete this financing during the current turmoil in the debt markets demonstrates the continued
good standing the Company has with its banks.
The Company’s remaining un-financed capital commitments in respect of its FSRU conversion
projects amount to approximately $80 million in respect of the Golar Freeze project. The current
level of debt associated with the Golar Freeze is approximately $30 million and its charter as an
FSRU will generate total revenues over 10 years of around $450 million. The Company has had
positive discussions and responses from a number of banks in connection with the refinancing of the
Golar Freeze and the Board therefore remains confident that the Company will be able to refinance
the Golar Freeze and improve the company’s liquidity position even in today’s difficult market
conditions. In the unlikely event that a refinancing is not achievable in the current credit market the
Board believes that alternative sources of short-term financing will be available in order to meet
capital commitments in respect of the Golar Freeze.
Currently approximately 67% of the Company’s debt and net capital lease obligations are effectively
swapped to a fixed rate. The Company’s current total debt and net capital lease obligations are
approximately $1 billion. The total current cost of this debt based on the Company’s swap rates, 3
month Libor and average margin is approximately 4.5%.
Operational Review
Shipping
Trading performance of the Company’s vessels operating in the spot/short term market was slightly
improved over the quarter. Rates held up for the early part of the quarter however began to soften
toward year end. Further deterioration has occurred into the first quarter of 2009 although activity is
just now beginning to again increase.
Granatina, now renamed Golar Arctic, was redelivered from a 12 month charter with Shell in
January and the vessel’s technical management has been transferred to Golar. The Golar Arctic will
continue to maintain the Company’s presence in the spot/short term market in the period following
the delivery of Golar Frost in June 2009 to OLT-O for the Livorno FSRU project. Golar Frost was
redelivered from its 4 month charter to Morgan Stanley in November 2008 and will continue to be
available for short term charters until redelivery to OLT-O in June 2009.
The new-build in-charter, Ebisu, remained on hire to the North West Shelf project throughout the
quarter at a profitable rate.
Vessel operations remained smooth and incident free throughout the quarter.
Regasification
Following the completion of construction by Petrobras of the shore side facilities in Pecem, Brazil,
Golar Spirit completed final commissioning and start up activities associated with the floating
storage and regasification (“FSRU”) conversion project. Commissioning was followed by a series of
performance test runs which formed part of the delivery protocol for the vessel. The commissioning
and start up was successfully concluded without incident and with Petrobras kindly acknowledging
the high standard of professionalism provided by the Golar technical team involved in the delivery
of the project. The Golar Spirit will soon sail to Rio to commence commissioning activities in
advance of the arrival of Golar Winter.
Golar Winter arrived at Keppel ship yard in Singapore on September 29, 2008 to commence Golar’s
second FSRU conversion project. The FSRU is scheduled to deliver to Petrobras in Guanabara Bay,
Rio de Janiero during Q2 2009. All major equipment items for the vessel conversion have now been
installed onto the vessel and work continues to integrate the new equipment. The Company is
satisfied with the progress being made with the project and pleased to see the experiences and
learning from the Golar Spirit project transferred to the Golar Winter project.
Detailed engineering for the Golar Freeze FSRU project is continuing with major equipment items
required for the vessel conversion being ordered consistent with the vessel’s scheduled delivery.
Discussions have commenced with shipyards to finalise the contract for the vessel conversion.
Discussions are continuing with the OLT-O (Livorno) joint venture in support of the Golar Frost
conversion project and possible future roles for Golar within the project which includes amongst
other things operation and maintenance of the terminal.
Petrobras advised during the quarter that due to the current economic environment it is not intending
to continue with its tender to secure a third FSRU. The disappointment in this development is to a
large extent offset by the continuing high level of interest in FSRUs from other parts of the world.
This interest has been spurred on in recent months due to gas supply disruptions in Europe and an
expected increase in the supply of LNG from producing projects.
Liquefaction
The Company was pleased to recently announce the signing of a Heads of Agreement (“HOA”) with
project developer Liquefied Natural Gas Ltd (LNG Ltd) formalising Golar’s participation in the
Gladstone LNG (“GLNG”) project. GLNG, the project company, is intending to develop a mid-scale
(1.5 million tonne per annum) liquefied natural gas plant in the Port of Gladstone, Australia. The
plant will purify and liquefy coal seam gas sourced from gas fields, located in Central Queensland,
north east Australia. The current estimated development cost for the LNG facility is approximately
$500 million. First production is currently scheduled for 2012. The project also offers attractive
expansion opportunities.
Final investment decision and financial close of the project is expected toward the end of 2009. Of
key importance to this final decision will be successful financing of the project and funding of
Golar’s participation in a way that is accretive to shareholders. Until a final investment decision is
made there is minimal financial commitment required from Golar. The terms of the HOA include
Golar’s 40% equity participation in the project and the full LNG output from the project on an FOB
basis. In parallel to the negotiations with LNG Ltd with respect to the purchase of the LNG, Golar
has progressed discussions to sell its offtake on a delivered, long term basis to a credit worthy LNG
buyer. Delivery of the LNG will utilise up to two of Golar’s existing LNG Carriers. Golar anticipates
that, in addition to the financing to be raised at the project level, it will also be able to raise financing
in connection with the offtake and shipping arrangements. The formalising of Golar’s role in the
project is a significant milestone in the achievement of the Company’s midstream LNG strategy.
The Company continues to make good progress, working in partnership with PTTEP, in developing
Floating LNG projects. Activity has progressed over the past quarter from screening stranded gas
opportunities to maturing the most attractive of the identified opportunities. Detailed activity is now
focused on 2 to 3 specific upstream assets. Of note is the recent acquisition by PTTEP of Coogee
Resources with operations located in the Timor Sea, Western Australia. Both companies believe that
Coogee may provide an attractive platform for the development of a FLNG project.
Market
The short supply of LNG to energy markets in 2008 is likely to turn into plentiful supply as four new
LNG producing projects come on line amid a global financial crisis and recession in many LNG
consuming economies. Predicting the outcome of this market mix is even more difficult than usual
but some signs indicating the way forward are starting to emerge.
2009 will see the start of a capacity build provided by new plants that are currently under
construction in Qatar, Yemen, Russia, Peru, Indonesia, Australia, Angola, and Algeria. The new
capacity will form the backbone of an approximate 30% (40 million tonnes) rise in total global LNG
production by the end of this year and an increase by some 60% in worldwide capacity over the next
4 to 5 years. Production will rise from approximately 175 million tonnes in 2008 to around 290
million tonnes by 2013. No other globally traded commodity can confidently anticipate this level of
growth over the next few years.
What is perhaps less clear is the actual destination for this rise in LNG production. Early signs are
that Far East markets may not provide the support once relied upon by LNG traders. The economic
downturn is depressing demand for power generation in the established markets of Japan, Korea and
Taiwan and the appetite for incremental LNG in the more recently opened markets of China and
India is still to be fully tested. Interestingly there are signs of Pacific Basin production already
starting to trickle into Europe. Should this trend continue as new Far East capacity comes on stream
we might soon see more Pacific Basin produced cargoes head for the more liquid markets of the US
and Europe. This would represent a complete reversal of the trading pattern that has characterised
the LNG market in recent years from tradable cargoes produced in the Atlantic Basin being drawn
East to a market where marginal production in the Pacific Basin is looking for a home in the Atlantic
Basin - as previously existed in the period 2002 to 2004.
As new LNG capacity comes on stream, the length currently observed in the short term LNG
shipping market is expected to rebalance, with ships finally entering employment on a long term
basis with the intended projects. Additionally, conversion projects and scrapping of older vessels
continue to gain momentum. The ratio of available spot vessels to worldwide LNG production is set
to decline in the next few years with no expected reduction in long haul trades. Spot charter rates
will stay depressed for the first half of 2009 but there is reason to expect steady improvement in the
situation from mid year.
Outlook
The LNG shipping spot market continues to suffer from a delay in the start up of new LNG
production capacity resulting in a surplus of shipping and more recently, the downturn in the global
economy. The first half of 2009 will be a difficult trading environment for the Company’s spot
trading ships with a reduction in earnings anticipated for the first quarter 2009. However, there is a
realistic hope for improvement in the second half of 2009 as new capacity comes on stream and
cargoes start trading west. The Board continues to believe that the long-term outlook for LNG
demand in global markets remains strong and that production capacity currently under construction
will progressively improve the situation.
The company’s strategy of diversifying into FSRU’s and over time into liquefaction is and will
continue to deliver a more robust revenue profile as the broader LNG market moves through the
different phases of the economic cycle. Furthermore, the company’s committed FSRU contracts
delivering over the next 18 months will add significantly to operating cash flow.
Golar LNG Limited
|