Preparations to use the Discoverer Enterprise to deploy the LMRP cap and the intended severing of the damaged riser mean that the riser insertion tube tool, previously deployed, will not be reinserted into the main leak at the end of the riser. Work on the first relief well, which started on May 2, continues and it has currently reached a depth of 12,090 feet. Work on the second relief well, which started on May 16, had reached a depth of 8,576 feet before drilling was temporarily suspended on May 26. Drilling operations on the second relief well resumed on May 30. Both wells are still estimated to take around three months to complete from commencement of drilling. Surface Spill Response and Containment Work continues to collect and disperse oil that has reached the surface of the sea, to protect the shoreline of the Gulf of Mexico, and to collect and clean up any oil that has reached shore. Over 1,600 vessels are now involved in the response effort, including skimmers, tugs, barges and recovery vessels. Operations to skim oil from the surface of the water have now recovered, in total, some 321,000 barrels (13.5 million gallons) of oily liquid. The total length of containment boom deployed as part of efforts to prevent oil reaching the coast is now over 1.9 million feet, and an additional 1.8 million feet of sorbent boom has also been deployed. So far approximately 30,000 claims have been submitted and more than 15,000 payments already have been made, totalling some $40 million. BP has received more than 110,000 calls into its help lines to date. Additional information The cost of the response to date amounts to about $990 million, including the cost of the spill response, containment, relief well drilling, grants to the Gulf states, claims paid and federal costs. It is too early to quantify other potential costs and liabilities associated with the incident. BP press release |