The Accommodation Block Lifting of No.33 BC Completed

2 July 2015



On the morning Of July 1, the No.33 64K bulk carrier had the accommodation block lifted and installed.


The Integrity of the Accommodation Block Lifting for No.33 64K BC Improved

2 July 2015

The No.33 64K bulk carrier was scheduled for accommodation block lifting on June 30. During the eighty days since the pre-erection lifting on this April 7, the accommodation project team dedicated themselves to optimizing their production procedure, making excellent plans, and overcoming numerous difficulties, thus attributing to this vessel with the best integrity of accommodation lifting this year.


Image by Chengxi Shipyard Co., Ltd.


Image by Chengxi Shipyard Co., Ltd.

Chengxi Shipyard Co., Ltd. press release