N192 Taking Shape
13-7-2010
With the erecting of the F31 block, the 11th 57,000DWT bulk carrier N192 being built for the ER company, its construction of the main hull was smoothly completed in COSCO Guangdong Shipyard on the afternoon of May 14th.
The keel of the vessel was laid on 15th of March.
After careful planning, only 60 days were required to finish the fixed main body shaping node task.
COSCO Shipyard Group Co. Ltd. press release
|