Amendments to Shipbuilding Contracts
Hong Kong, 13 December 2010
Reference is made to the Announcements and the Circulars in connection with, inter alia, the
Shipbuilding Contracts entered into by the Purchasers respectively with the Sellers for the
construction of the Vessels.
On 13 December 2010, the Purchasers each entered into an addendum to each of the
Shipbuilding Contracts with the Sellers to revise the date of delivery of the Vessels.
Revision of Delivery Dates
On 13 December 2010, the Purchasers each entered into an addendum to each of the
Shipbuilding Contracts with the Sellers, pursuant to which the date of delivery of the First
Vessel has been revised from the fourth quarter of 2012 to the first quarter of 2013, the date
of delivery of the Second Vessel has been revised from the second quarter of 2013 to the
fourth quarter of 2013, the date of delivery of the Third Vessel has been extended one month
and remaining in the first quarter of 2013 and the date of delivery of the Fourth Vessel has
been revised from the second quarter of 2013 to the fourth quarter of 2013, with all the other
terms of the Shipbuilding Contracts remaining unchanged.
Orient Overseas (International) Limited (OOIL)
|