Statements by Port of Hamburg Marketing Executive Board Members Axel Mattern and Ingo Egloff on Today’s Decision by the Federal Administrative Court 02. Oct 2014 We respect the decision announced today by the Federal Administrative Court (FAC) in Leipzig on the deepening and widening of the navigation channel on the Lower and Outer Elbe. A final decision can only be taken when the European Court of Justice (ECJ) has clarified questions still outstanding on the so-called prohibition of deterioration and desirability of improvement embodied in the European Water Framework Directive. These questions will be resolved by spring 2015 in connection with complaints against a deepening of the River Weser. The FAC also emphasized, however, that while the environmental compatibility assessments in respect of the fauna/flora done for the planning approval for the deepening of the navigation channel of the Lower and Outer Elbe exhibit various shortcomings, in its opinion these can be overcome and should not lead to a lifting of the said approval.
Two passing containerships on the Elbe. Image by Port of Hamburg
Press Release of the Federal Administrative Court (No. 58/2014) Dredging the River Elbe: Waiting for Luxembourg The Federal Administrative Court in Leipzig today adjourned the proceedings by the BUND and NABU environmental associations against the plan approval concerning the dredging of the lower and outer stretches of the river Elbe until the Court of Justice of the European Union (CJEU) in Luxembourg has reached a decision regarding a pending referral of the interpretive ruling on the Water Framework Directive. The 7th division of the Federal Administrative Court, which is responsible for waterways law, last summer ruled against the expansion of the river Weser under the Water Framework Directive after objections from environmental associations. With its decision of 11 July 2013 (BVerwG 7 A 20.11), the Federal Administrative Court presented the ECJ with a range of questions concerning the Water Framework Directive’s so-called prevention of deterioration and requirement for improvement (cf. press release No. 47/2013 from 11 July 2013; EuGH C-461/13). The ECJ’s decision is prejudicial to the proceedings regarding the dredging of the river Elbe because the referred questions can also be raised here. The referred questions’ relevance to the decision is still valid as a result of the first supplementary resolution passed on 1 October 2013. In the supplementary resolutions, the respondents have supplemented the plan approval dated 23 April 2012 with the authorisation of a precautionary exception to the management objectives for the bodies of water affected. The “review of assistance” employed is not sound, however. For this to be the case, the criteria applied to evaluate the supposed deterioration in the state of the water would have had to be defined in the supplementary resolution and its factually reinforced meaning presented in a comprehensible manner. This has not happened to a sufficient extent. Following the five-day hearing in July 2014, when the German Federal Waterways Engineering and Research Institute’s expert opinion on the plan’s effects on tide levels, flow and sedimentation rates, traffic requirements and the review of alternatives, as well as the extent to which protected animal and plant species (e.g. Elbe water dropwort, twait shad, maraena whitfish, red knot) may be affected had been debated, the 7th division also deliberated on the other points of conflict. According to its preliminary assessment, the plan approval is, indeed, burdened by various shortcomings as regards its environmental impact and habitats directive assessment. These shortcomings can be addressed, however, and will not lead to the revocation of plan approval, either individually or as a whole. The ECJ’s decision in case C-461/13 must therefore be made before the 7th division can make its final decision. The hearing at the ECJ took place back on 8 July 2014, but a decision is not expected until spring 2015. Source: BVerwG 7 A 14.12 – Ruling of 2 October 2014 (www.bverwg.de) Further Statements on Today's Decision by the Federal Administrative Court Klaus-Dieter Peters, Chairman of the Executive Board of Hamburger Hafen und Logistik AG: “We regret the continued delay of the urgently needed dredging of the river Elbe, which comes into effect with today’s ruling by the Federal Administrative Court. What’s pleasing, however, is that the court found no shortcomings in the plan approval, which could lead to the approval being revoked. We now eagerly look forward to the Luxembourg based European Court of Justice’s interpretive ruling on the Water Framework Directive. We still very much hope that the construction activities will start soon. However, irrespective of the court’s decision we will continue with our efforts to further boost the efficiency of our facilities’ handling operations. HHLA will also continue to pursue its Intermodal strategy, which links the seaports and the European hinterland through logistics chains that serve as exemplary models in both economic and environmental terms.” Port of Hamburg press release |