CHI (Guangdong) Completes Ruchun Painting in 99 Hours


19 November 2025


Facing confined workspace in Cuihuashan floating dock, CHI(Guangdong) optimized crew deployment and dynamically adjusted workflows to safely strip 9,070m2 of old coatings from the flat-bottom hull and 2,200m2 from port / starboard freeboard areas.

The team then applied five-coat painting to the entire hull and seven-coat painting around the scrubber overboard discharge outlet.

To minimize dock time, the shipyard implemented a "pre-dock preparation" strategy:

Pre-docking robotics: Used smart painting robots to pre-strip 1,600m2 of hull coatings above waterline during berthing

Early access operations: Deployed aerial platforms for ultra-high-pressure water blasting on starboard freeboard

This enabled immediate full-scale operations upon docking. The project set new efficiency benchmarks:

Completed 11,300m2 hull stripping (including pre-dock work), dual high-pressure washing, and first-coat application within 51 hours of docking. Achieved full painting sequence in just 99 total hours - slashing the dock time by 40% compared to conventional methods.


Image by China COSCO Shipping Corporation Limited.

China COSCO Shipping Corporation Limited, press release